Rails To Trails Conservancy
Better Business Bureau Accredited Charity
shop   |   eNews   |   find a trail
Share this page:
Moonville Rail-Trail Saves Money by Using Old Rail Cars as Bridges

Photo and story by Eric Oberg/Rails-to-Trails Conservancy

Bridges are a costly need for rail-trails, many of which cross streams, roadways and even other rail corridors. After engineering and installation quotes were obtained from a precast bridge supplier for bridges along Ohio’s Moonville Rail-Trail, the reality of the extremely costly challenge became clear. So when members of the trail’s nonprofit group heard that old flatbed rail cars might be available from the federal government’s Gaseous Diffusion Plant near Piketon, Ohio, a light bulb went on and calls were made. The rumor was true: some rail cars were available to eligible entities, including nonprofits. Over the next few months the trail group expressed its interest, then waited, worried and wondered what needed to be done to get the cars to their corridor. Moonville Rail-Trail President Neil Shaw finally got the call in August and was informed that three cars were ready for pick-up.

Although the cars were donated at no charge, they had to be moved within three days to avoid a stiff storage fee. A friend of the trail with a big rig and trailer came to the rescue. Just shy of the move deadline, three rail cars were being backed down the corridor toward the first bridge site. The rail cars are heavy steel flat bed cars, as if they were manufactured to someday work as a bridge structure.  The sheer strength, size and shape made these cars ideal bridges.

Two large cranes were rented for lifting the cars off of the trailer and then placing them on the existing bridge abutments. As the cars were scrutinized it was found that they were actually not 50 feet long, as advertised, but were instead 46 feet, nine inches long. With bridge abutments exactly 50 feet apart at the first site, some good old-fashioned ingenuity was needed. The contractor working to install the bridges, Seneca Steel from nearby Logan, Ohio, was more than up to the task. Using portable truck-mounted welding equipment, the contractor fabricated extensions for each end of the rail car, as well as feet that were then bolted to the abutments to make the elevation work to match the adjoining trail tread. This amazing work has resulted in a snugly fit bridge structure that should service the trail for decades to come.

The second bridge site was an even larger challenge. The opening from abutment to abutment was measured at 54 feet, and again the rail cars were only 46 feet, nine inches. The torches came out and the more than seven feet necessary to finish the span was simply cut from the third rail car. This piece will be welded onto the car and the bridge placed on the abutments. 

The Moonville Rail-Trail now boasts two bridge decks in need of decking and railings. Until now, the bridges have cost the group under $4,000 for transportation and installation work.  They are currently soliciting bids for the wood necessary to complete the projects. The original quote for building, transport and installation from the pre-fab company was $54,000 for the first bridge and $84,000 for the second. What trail group, looking at a huge capital need such as a bridge project, cannot appreciate a savings of more than $100,000?


Posted Wed, Oct 21 2009 11:19 AM by Stephen Miller (RTC)

Comments

Jennifer Hill wrote re: Moonville Rail-Trail Saves Money by Using Old Rail Cars as Bridges
on Thu, Oct 22 2009 5:02 AM

Thank you for putting up this story, it is a very promising way to get more bridges for less money.

However, I'm not sure what this is a photo of?  Is it one of the flatbeds now welded in place? The holes make me wonder. After reading the article, I'm guessing that decking will be constructed on top of this metal?  Which one of the two bridges is the image?

Response from Eric Oberg: This is indeed one of the bridges, the first one in the story.  The decking will be wide and thick hardwood boards, there are actually holes in just the right spacing along the edges of the rail car which will allow for bolts to be used to hold a stringer piece of wood that will run the length of the car.  The actual deck boards will then be laid on top of the stringer, perpendicular to the rail car, and fastened into place into the wooden stringer.  There are also strategically placed holes along the edge of the rail car that are perfectly sized to allow 4x4 posts to be inserted for the handrail posts!

John Wells - a.k.a. the ToolBear wrote re: Moonville Rail-Trail Saves Money by Using Old Rail Cars as Bridges
on Fri, Nov 6 2009 9:19 PM

Interesting idea.  I have sent the blip to two rail-trail organizations I belong to Out West.  

Another option, which I have seen on the Cascade Trail in Skagit County, WA, is to use the body of a flatbed trailer.  My photo of that may be on the Cascade Trail page.  It's over at the HikeABike Swamp crossing on the trail.

May be more of those around that rail cars.

What else can we think of that would work?

Add a Comment

(required )
(optional )
(required )  
Remember Me?
 

Rails-to-Trails Conservancy
The Duke Ellington Building
2121 Ward Ct., NW
5th Floor
Washington, DC 20037
+1-202-331-9696